A performance-based design brief (PBDB) sets out the scope, technical basis and acceptance criteria for a proposed Performance Solution. For a JV3 assessment, formally called J1V3 in NCC 2022, preparing the brief in consultation with relevant stakeholders forms part of the required Performance Solution process. Establish it before carrying out the compliance analysis.
Ask your energy assessor to coordinate the technical brief with the relevant project participants. Confirm what will be assessed, which NCC edition applies, who supplies the information and how compliance will be demonstrated. This gives your Section J assessment a clear starting point while design decisions can still be coordinated.
Code context: This guide explains the NCC 2022 process. Apply the edition, amendments, jurisdictional variations and approval requirements that govern your project, including any different requirements where NCC 2025 applies.
Where does the PBDB fit in a JV3 assessment?
Under NCC 2022, the Performance Solution process involves four stages:
- Prepare the performance-based design brief through the required consultation.
- Carry out the proposed analysis.
- Evaluate the results against the acceptance criteria.
- Prepare the final report documenting the outcome and any conditions.
Using a prescribed Verification Method such as J1V3 does not remove this process. The level of detail should suit the complexity and scope of the solution.
For the subsequent modelling stages, see our JV3 and J1V3 modelling process.
Who prepares and agrees to the brief?
For an energy assessment, the appointed assessor can prepare the technical content, with the lead designer or project manager coordinating contributions. Relevant participants may include the owner, architect, services engineers and builder, depending on the project stage and scope.
Confirm the approval authority’s expectations for the assessment method and documentation while preserving its independent assessment role. The certifier or building surveyor should not be asked to design the solution they will later assess.
Record the relevant participants’ agreement, comments and responsibilities. Confirm the required endorsement format for the project; a universal signature list should not be assumed. Agreement on the brief does not itself establish that the completed design complies.

What should a JV3 performance-based design brief include?
Use the following checklist to organise the project-specific information. The brief should make the proposed assessment understandable to someone who was not involved in the initial discussions.
| Brief component | What to record |
|---|---|
| Project and code basis | Address, building classification, use, assessed areas, applicable NCC edition and relevant local requirements |
| Proposed solution | The design being assessed, the reason for the Performance Solution and its boundaries |
| Performance Requirements | Requirements relevant to the solution, including requirements affected elsewhere in the building |
| Assessment method | The nominated Verification Method and any other assessment methods needed for the agreed scope |
| Acceptance criteria | The specific benchmarks, comparisons and internal-condition criteria used to judge the outcome |
| Inputs and assumptions | Drawing revisions, constructions, glazing, shading, services information and unresolved assumptions |
| Responsibilities and evidence | Who supplies each input, performs the analysis, checks the information and provides supporting evidence |
| Reporting and consultation | Required report content, limitations, participants, review comments and the record of agreement |
Keep detailed drawings and schedules in a referenced document register where practical. Our Section J and JV3 document checklist helps organise those supporting inputs.
Make the acceptance criteria specific
“Achieve Section J compliance” does not explain how the assessment will be judged. The brief should identify the applicable criteria and how each will be demonstrated.
For an NCC 2022 J1V3 assessment, that includes the required proposed-building and reference-building emissions comparisons, the thermal-comfort assessment and the additional requirements in Specification 33. Identify the relevant modelling parameters and profiles as well.
Record the actual applicable thresholds, assessment conditions and evidence requirements in the project brief. Stakeholder agreement cannot replace a mandatory criterion. If using another NCC edition, review its requirements before adopting criteria from an earlier project.
An illustrative PBDB scope for a Class 5 office
Consider an office project where the design team wants to test a proposed glazed façade through J1V3. A useful brief could establish:
- Design question: whether the nominated façade and building design satisfy the applicable J1V3 criteria.
- Assessment boundary: the identified office areas, envelope elements and relevant services, with exclusions and interfaces recorded.
- Design inputs: nominated architectural revisions, whole-window specifications, construction assemblies and services schedules.
- Method and criteria: the applicable reference-building comparisons, internal-condition checks and supplementary compliance evidence.
- Responsibilities: the architect confirms geometry and shading; the relevant consultants confirm services inputs; the assessor develops and checks the assessment.
- Outstanding decisions: unresolved glazing selections or services assumptions, with a responsible person and confirmation date.
- Deliverable: a report explaining the analysis, results, required specifications and any conditions or limitations.
This is an educational example, not a completed or approved PBDB. The project team must develop the actual brief, criteria and consultation record for the building being assessed.

How does the PBDB differ from the final JV3 report?
The PBDB establishes the assessment plan: what will be investigated, which criteria apply and what evidence will be provided.
The final report documents the completed assessment: the design analysed, methodology, results, compliance conclusion, specifications and any conditions or limitations.
The report should connect the evidence to the agreed brief and explain material changes to the assessment basis. A signed brief or a software output alone does not provide the complete Performance Solution documentation. For help interpreting the eventual deliverable, read our Section J report example.
Keep the brief aligned with design changes
Review the brief when a change affects its scope, method, criteria or underlying assumptions. Examples include a different building use, revised assessment boundary or a change to the nominated compliance approach.
For ordinary design revisions, keep the input register and model records current, then confirm whether the brief also needs updating. A minor drawing change does not automatically require a completely new PBDB, but its effect on the assessment still needs consideration.
Frequently asked questions
Can I use a generic PBDB template?
A template can organise the information, but the completed brief must describe your project and its applicable assessment basis. Replace inherited assumptions, identify the actual participants and complete the required consultation. A template with only a new address is unlikely to explain a different design adequately.
Does a simple JV3 project still need a brief?
Under the NCC 2022 Performance Solution process, simplicity does not remove the brief stage. Keep its detail proportionate to the solution and confirm the project’s documentation requirements with the relevant authority.
Arrange your Section J assessment scope